PROJECT BLUEORION
Project BlueOrion

Mission Report 01 · 2026

October Edition

Lift-off: our first month on site

The Sydney Water works done in four business days, the block cleared and set up, and excavation down to rock.

Aerial view of the BlueOrion site, a cleared block between established neighbouring homes
The block from above, among established neighbours on a narrow, car-lined street.

Days on site

Since 1 October 2026

23

Phase

Bulk excavation

Next milestone

Piers drilled, inspected and poured

Flight Path

Progress since the last report

  • Took possession on 1 October. Fences up and Sydney Water works under way within 24 hours.
  • Completed the Sydney Water works. See the Briefing below.
  • Cleared the overgrown trees. See Course Corrections.
  • Set up the site: fencing, a 24/7 security camera, temporary power and water, a sewer-connected toilet and a site office. The surveyor set out grids, benchmarks and levels.
  • Started bulk excavation: an old septic tank, buried brickwork and clay pipes removed, and now down to rock. No asbestos found in our works.
Gravity Projects branded site fencing and construction signage
Secure fencing, banner mesh and signage.
Survey set-out plan showing building grid lines, benchmarks and reduced levels
The survey set-out every trade builds from.
An old concrete septic tank lifted out of the ground during excavation
An old concrete septic tank, lifted out.

Briefing

One part of the build, explained in depth

The Sydney Water works

A Sydney Water sewer runs across this block, and normally you can't build over one. We obtained a Building Plan Approval to do it, on the condition the pipe is encased in concrete, so if it ever cracks the sewage stays in its channel instead of leaking under the homes.

Old clay sewers like this one are almost always cracked once uncovered, which usually means a modified approval, a bypass and a new pipe anyway. So we replaced it with new PVC from day one and encased that. No surprises, and no camera survey of the old line needed.

In the same works we bored under the road for water instead of trenching it, avoiding road permits, bonds and disruption, and gave each home its own water service and meter. The homes will be on separate Torrens titles, so the middle home also got its own sewer side line. All done in four business days.

Next, the piers beside the sewer go into rock below its zone of influence, so the homes' weight bypasses the pipe. They are inspected by our Water Servicing Coordinator and the certifier before pouring, which leads to the Section 73 Compliance Certificate the homes need before they can be occupied.

Sydney Water plan showing the sewer main to be replaced and concrete encased from A to B, and the existing junction extended as a new side line
The approved plan: the main replaced and encased from A to B, and the existing junction extended as a new side line.
New white PVC sewer side line extension laid on supports in a trench
The new sewer side line extension, before encasement.
Concrete poured along a trench to encase new sewer pipework, with connection risers standing above it
Concrete encasement poured around the new sewer works.
A tree root found growing inside a broken terracotta clay pipe on the site
Why we don't trust old clay pipes: a root growing inside one on this site.

Flight Plan

What's next on site

  • Next 1 to 2 weeksFinish bulk excavation, cut and fill down to the underside of the slab.
  • ThenDetailed excavation: garage and wet area set-downs, footings and piers.
  • Pour 175 piers socketed into rock. Those beside the sewer are inspected before pouring.
  • Pours 2, 3Strip footings, then the ground floor slab.
  • AlongsideRetaining walls on the neighbouring boundaries.
  • Behind the scenesSteel frame and truss shop drawings, so frames arrive as the slab is poured. More on the steel system next month.

Wins

What went well this month

The old brick shed fitted out as the site office, with a new door and air conditioner

A site office with history

Clearing the trees uncovered an old brick shed. Rather than hire a site shed, we fitted it out as our site office, and it has turned up a few treasures from decades past.

One pole, not two

Construction power runs from the permanent pole for the middle home, so there is no temporary pole to install and relocate later.

The team is locked in

Most trades are appointed, from excavation and concrete to windows, joinery and the staircase. Brickwork and roofing go to tender next. Early procurement protects the programme and gives our client and lender confidence.

Course Corrections

Challenges, and how we solved them

The block after the overgrown trees were removed

Trees that outgrew the block

Decades without maintenance left snapped branches and roots damaging nearby properties. We even found roots inside old clay pipes. The trees permitted for removal are gone, under an arborist clearance and with the neighbours' support.

An excavator working on bulk excavation beside the boundary fence

Rock without the racket

We have reached rock and so far removed it without jackhammers, working within vibration limits to keep noise down for the neighbours.

Beating the weather

Open footings fill with rain, costing time and pump-outs. So each pier or footing is poured as soon as it is dug, across three pours: piers, footings, slab.

Quality Log

Inspections, tests and certificates

  • Dilapidation reports: street and both neighboursComplete
  • Arborist clearance for tree removalObtained
  • Sydney Water Building Plan ApprovalApproved
  • New PVC sewer and concrete encasementSigned off
  • Work-as-executed plans for the sewer worksSubmitted
  • Survey set-out: grids, benchmarks and levelsComplete
  • Asbestos in our worksNone found
  • Piers beside the sewer inspectedBefore each pour
  • Section 73 Compliance CertificateAfter pier sign-off

Ground Control

Notes for neighbours and the community

Work hours

7am to 5pm. We avoid Saturdays, and if we do work one, no loud work that day.

Your property, on record

Dilapidation reports on the street and both neighbours were done before we started, so existing and new marks can be told apart.

Less traffic

Rigid trucks only, no truck and dog trailers, and a sewer-connected site toilet means no pump-out trucks.

Christmas and New Year

No unnecessary work over the break, and only quiet work on days that are not public holidays.

Thanks for following along. Anything on site affecting you? Contact us directly and we will sort it out.

shane@gravityprojects.au0410 575 685Next report: November 2026

Mission Reports summarise progress for a general audience. Programme dates are targets and can change. A Blueorion development, built by Gravity Projects.

Stay on the frequency

Get the next BlueOrion report.

Get each Mission Report in your inbox the day it lands. Pick the builds you care about and leave whenever you like.

  • One report a month per project you follow. Nothing else unless you ask for it.
  • Progress, the month ahead, what went well and what we solved.
  • A heads-up on site activity that affects the street.